House Report, Week 2

This is the second report on what has been happening with the construction of the house. Remember, you can get a daily detailed report by following the updates on Google+!  To conserve the space on the blog, you're going to have to click the read more link to get the report.
Apr-2 Monday


The team wrapped up the retaining wall, getting a lot more done in terms of finalizing the length and height of the it. They also had gotten the utility people out to mark where the cables are buried in our backyard, so we aren't quite sure what they are going to do in terms of terracing or leveling our backyard.

Apr-3 Tuesday

It was a stormy day, so no work was done on the lot.
Go to Google+ Pictures

Apr-4 Wednesday

They did a bit more cleanup and finalizing of the retaining walls and leveling of the property. Not much else to tell on that day.

Apr-5 Thursday

When we came today, no work was done... we aren't quite sure why. So, let's just call it a Glitch Day.
Go to Google+ Pictures

Apr-6 Friday

The plumber finally came today to work on our sewer line, extending it to our house. A company called Hill & Company was contracted to do the work, and as far as we can tell they did a good job. The regular team did not do any other work on the lot.


the Week in Review
Less work than we expected was done this week, due to no work being done on two days. We are now waiting for the city inspector to approve the work done by the plumber, then we can get on with finally finishing the retaining walls and moving on to the foundation.

Remember, the blog will not be updated every weekday with pictures, you will have to go to our Google+ page to look at our daily updates. Click the banner at the top of the blog to go!

Also, visit our website to view the timeline for building our house... it provides a good overview of what to expect.

Thanks for following!
Brother

No comments:

Post a Comment

We enjoy hearing feedback. You can leave a note here.