Monday, July 9, 2012

House Report, Week 14




This is the report on what has been happening with the construction of the house. Remember, you can get a daily detailed report by following the updates on Google+!  To conserve the space on the blog, you're going to have to click the read more link to get the report.


Hey, just a quick note before we start: most of what's happening right now is better seen than written, so click on the links to check the pictures out!

July 2 Monday

Electrical people came back and cleaned up. Another team grounded the lightning protection system as well. We also got inspected for the electrical wiring and failed... again. The notice is included in the pics, but the gist of it is that the electrical team grounded the house to the wrong line, they forgot to wire the safe room, and they say that the central kitchen island needs to be wired up, even though it's planned for it to be removed.

July 3 Tuesday

Today, the data people came back and rerouted their wires to a hall closet for the central routing station. There was also a team of people searching for the power pipe that would let the electrician wire power to the kitchen bar on the outer edge of the kitchen. You know things are bad when they resort to using sledgehammers at random trying to find the end of that pipe.

July 4 Wednesday

As this day is a holiday, they did not work. Click the link if you didn't see our little greeting card.

July 5 Thursday

We hope and pray that the electrical team doesn't hate us, because they came back again to fix some errors and add some power plugs where they missed them on the map. Apparently the developer is the poor mediator between our dense electricians and our map... we got a note from him when we notified him of the changes still needed to be done saying that the team was starting to despise this house. The good news is that they found the end of the pipeline for wiring electricity to the kitchen bar.

Another team went around the house and taped up the cracks and holes in the siding in preparation for insulating and bricking the walls.

July 6 Friday

A team removed the central kitchen island piping today... all that's left of it is a dark gray smudge in the foundation. Now awaiting the inspector to reinspect the wiring.

July 7 Saturday

Sheetrock was delivered today, presumably in the morning. No other work was done, as this is the weekend. :P

the Week in Review

We should be on the brick soon! All that's left for the inside right now is inspection, sheetrock, and insulation... hopefully they'll finish by the end of next week! Stay with us, things are about to get very exciting!

Remember, the blog will not be updated every weekday with pictures, you will have to go to our Google+ page to look at our daily updates. Click the banner at the top of the blog to go!

Also, visit our website to view the timeline for building our house... it provides a good overview of what to expect.

Thanks for following!
Brother

2 comments:

  1. Hi that one is wonderful which is a legitimate good post. It will assist me a lot inside the related stuff which is very much ideal for me. Perfectly written I appreciate & must say good job
    Thanks to share this post.

    ReplyDelete
    Replies
    1. Thanks! I apologize if I was a bit harsh when writing that post, we all were getting a little exasperated. :P

      Glad you contributed to the house, hope you'll get to see the final product!

      Delete

We enjoy hearing feedback. You can leave a note here.